Ephrem Girma Sinesilassie, Syed Zafar Shahid Tabish, Kumar Neeraj Jha
发表日期
2017/9/18
期刊
Engineering, Construction and Architectural Management
卷号
24
期号
5
页码范围
757-773
出版商
Emerald Publishing Limited
简介
Purpose
Time overrun is one of the most significant issues being faced by Ethiopian construction industry today. For effective time performance, the successful execution of construction projects and keeping them within prescribed schedule is very important. The purpose of this paper is to determine the factors responsible for impacting performance of Ethiopian public construction projects.
Design/methodology/approach
Based on the literature and personal interviews of key construction professionals in Ethiopia, a list of 35 project performance attributes having strong effect on performance of the projects were identified and a questionnaire using these attributes were prepared and administered in Ethiopia. Statistical analysis of responses on the attributes segregated them into distinct sets of success attributes and failure attributes. The attributes were also subjected to factor analysis separately for better understanding …
引用总数
20172018201920202021202220232024148232019113
学术搜索中的文章