KC Iyer, KN Jha
发表日期
2006/8
期刊
Journal of construction engineering and management
卷号
132
期号
8
页码范围
871-881
出版商
American Society of Civil Engineers
简介
Over 40% of Indian construction projects are facing time overrun ranging from 1 to 252 months; the reasons for which are being studied by researchers to suggest possible remedial measures. This paper identifies 55 attributes responsible for impacting performance of the projects. These attributes were then presented to Indian construction professionals in the form of a questionnaire. Statistical analysis of responses on the attributes segregated them into distinct sets of success attributes and failure attributes. Factor analysis of sets of success attributes and failure attributes separately grouped them into six critical success factors and seven critical failure factors. In order to understand the extent of contribution these factors have on the outcome of a construction project, a second stage questionnaire survey was also undertaken. The analyses of responses of the second stage questionnaire led us to conclude that two …
引用总数
2006200720082009201020112012201320142015201620172018201920202021202220232024164149714181619293428303435203010
学术搜索中的文章