作者
Pablo Ballesteros-Pérez, E Sanz-Ablanedo, Daniel Mora-Melia, Mª C González-Cruz, José Luis Fuentes-Bargues, Eugenio Pellicer
发表日期
2019/7/1
期刊
Automation in Construction
卷号
103
页码范围
279-290
出版商
Elsevier
简介
Earned Value Management (EVM) is a well-known project management technique for monitoring project progress. Over the last 15 years, many promising EVM metrics have been proposed to get, among other improvements, better actual project duration and cost estimates. Papers comparing the performance of all these metrics are, however, scarce and sometimes contradictory.
In this paper, a simulation and empirical comparison of 26 deterministic project duration forecasting techniques under the EVM framework is developed. Among them, two new metrics: Earned Schedule min (ESmin) and Earned Schedule max (ESmax) are proposed. ESmin and ESmax offer a new and simpler activity-level calculation approach of the traditional Earned Schedule metric. Top performing (most accurate) metrics: Earned Schedule (ES), Earned Duration (ED) and Effective Earned Schedule (ES(e)) with Performance Factor 1 …
引用总数
20192020202120222023202418720127
学术搜索中的文章
P Ballesteros-Pérez, E Sanz-Ablanedo, D Mora-Melia… - Automation in Construction, 2019