Purpose The purpose of this paper is to select a suitable procurement method for steel
building construction in Sri Lanka following a systematic method which weigh, both
procurement selection factors and existing procurement systems. Design/methodology/
approach An abductive research stance is followed in this empirical study. Procurement
selection factors were selected through a critical literature review which was followed by a
quantitative questionnaire survey. The collected data were analysed using descriptive …
Purpose
The purpose of this paper is to select a suitable procurement method for steel building construction in Sri Lanka following a systematic method which weigh, both procurement selection factors and existing procurement systems.
Design/methodology/approach
An abductive research stance is followed in this empirical study. Procurement selection factors were selected through a critical literature review which was followed by a quantitative questionnaire survey. The collected data were analysed using descriptive statistical analysis and relative important index.
Findings
The critical literature review outlined 46 procurement selection factors, out of which 26 factors were very important in steel building procurement selection. Short construction period and higher constructability of design are ranked at the top with the highest priority rating factors. Management-oriented procurement system was selected as the most appropriate procurement system for steel building constructions within the Sri Lankan context.
Research limitations/implications
The study is limited to widely use three procurement systems in Sri Lankan construction industry. Yet, the process followed in selecting the most appropriate procurement system could be applied for other contexts. The implications of the study are mainly identifying management-oriented procurement as the most suitable procurement method for steel building construction in Sri Lanka.
Practical implications
The systematic procedure of procurement method selection for steel building construction may use in the Sri Lankan construction industry to limit the resource loss due to wrong selection of procurement.